Changes to ČEZ Distribution’s connection requirements from 1 September 2025

05.09.2025 06:00 Technical Information

The distribution company ČEZ Distribuce has issued new connection requirements. The main changes concern requirements for electricity storage equipment, which led to substantial revisions to Chapter 4, Technical requirements for generation and energy storage facilities. Several terms have also been reworded, along with other minor updates.

The applicable connection requirements depend on the date of the connection agreement or agreement on a future connection agreement concluded with the distributor. If such an agreement was signed before the issue date of the currently valid Connection Requirements, the previous requirements valid when the agreement was concluded continue to apply.

Key changes:

  • Section 1.2 Terminology now includes Temporary Operational Notification, Final Operational Notification, micro-source, island operation, electricity storage system operator, prevention of an emergency under Section 54(2) of Act No. 458/2000 Coll., reserved capacity, technical dispatch centres and control and monitoring centres, electricity storage equipment, and simplified connection. Simplified connection may be used for a micro-source or electricity storage equipment with an installed capacity of up to 10.8 kW.
  • In Section 3.1 Location of the electricity meter switchboard, Table 1 (installation heights of the switchboard and its components) now includes the installation disconnect switch. It must be at least 300 mm above floor or finished ground level indoors and at least 700 mm outdoors. Table 1: Installation heights of the electricity meter switchboard and its components
  • Section 3.2.1 now specifies that all circuit breakers and switching devices must be within the physical reach of one person operating the relevant meter or switching device. This requirement now also applies to the installation disconnect switch.
  • Section 3.3.1 Interface types provides more detail on interface options for AMM (smart metering) meters and relay boxes.
  • Section 3.4 has been slightly revised. Consumption points, meters, main circuit breakers, installation disconnect switches, apartment doors and other items must now be durably marked to improve identification.
  • Chapter 4 Technical requirements for generation and energy storage facilities has been almost entirely rewritten, including its subsections. The changes add specific technical and legal requirements for the design and connection of generation facilities, especially when combined with energy storage. Storage may use a battery energy storage system (BESS), supercapacitor, gravity storage, hydrogen production and consumption (H2), or heat stored in water or sand.
  • The former Chapter 5 on technical requirements for a standalone battery energy storage system connected to the low-voltage distribution system has been deleted. These requirements are now included in Chapter 4.
  • The chapter on technical requirements for a standalone consumption point providing frequency restoration reserve services with active power of 100 kW or more is now Chapter 5. Subsequent chapters have been renumbered accordingly; Chapter 5 has also been slightly revised.
  • Chapter 6 Technical requirements for a local distribution system (LDS) now includes related legislation and additional provisions concerning energy storage.
  • The table linking low-voltage Connection Requirements to common activities (VP_A) has no major changes. One row covering a new generation facility, micro-source or storage connected to an existing consumption point, together with reconstruction or an increase in installed capacity, has been split into two. For the installation disconnect switch under Section 3.4.3, the table still states that at consumption points without generation, for a new connection, the switch must be in the metering switchboard only for switchboards manufactured after 1 January 2026.

…and a few other minor updates.

The new connection requirements are effective from 1 September 2025.

The ČEZ Distribuce Connection Requirements and appendices can be downloaded here: ČEZ Distribuce connection requirements (low voltage).

Please note: Consumption points established under connection agreements or agreements on future connection agreements signed before the issue date of these Connection Requirements remain subject to the previous requirements valid when those agreements were concluded.


We continuously incorporate the latest requirements into the manufacture of our electricity meter switchboards, so we can continue to guarantee that our switchboards comply with the connection requirements!