EG.D postpones the new metering switchboard wiring scheme until 1 January 2026

28.03.2025 09:00 Technical Information

Some time ago, we informed you here that the wiring of electricity meter switchboards for PV systems and electric mobility would not change from 1 July 2024 in EG.D’s distribution area, and that the change had been postponed until 1 July 2025. It has now been postponed again: the new wiring will be required from 1 January 2026.

Extract from EG.D’s email dated 28 March 2025:

Dear business partners and customers…
For unforeseen technical reasons, we must postpone the effective date of Diagram 16 until 31 December 2025 (the diagram for metering with a direct three-phase meter and active power control of renewable generation by a relay box, from 0 kW to 100 kW inclusive, effective from 1 July 2024) in the document “Requirements for the location, design and wiring of metering equipment at customers and small generation facilities connected to the low-voltage electricity network.”
Until then (31 December 2025), Diagram 15 will remain in force (see below). It requires an OR control relay to block appliances.

Diagram 15: Metering with a direct three-phase meter with transformer, active power control of renewable generation and ripple control receiver (0–100 kW inclusive), effective from 1 July 2022.


Switchboards must therefore continue to be fitted with an auxiliary OR relay. The existing PER 2F/3f/xx switchboards meet this requirement.

Preview Recommended type
PER 2F2/3f/xx/EGD

Recessed / wall-mounted
PER 2F/3f/40 recessed
PER 2F/3f/63 recessed

Pillar-mounted
PER 2F/3f/40 pillar-mounted
PER 2F/3f/63 pillar-mounted

This information is not yet available on the distributor’s website. The currently valid connection requirements still show the date 1 July 2024.
More information is available on EG.D’s website:
EG.D requirements for consumption points.

Our switchboards always meet all requirements and changes to the connection conditions. See our overview of switchboards suitable for EG.D here.


Abbreviations:

  • EG.D – distribution company of the E.ON Group. Its distribution area covers the South Bohemian, Vysočina, South Moravian and Zlín regions.
  • ČEZ Distribuce – distribution company of the ČEZ Group. Its distribution area covers the Central Bohemian, Plzeň, Karlovy Vary, Ústí nad Labem, Liberec, Hradec Králové, Pardubice and Moravian-Silesian regions, and parts of the Olomouc, Zlín and Vysočina regions.
  • EMO – electric mobility