ČEZ Distribuce issues new connection requirements, effective 1 February 2025

06.02.2025 10:00 Technické informace

The distribution company ČEZ Distribuce has issued new connection requirements. The key change is that an installation switch is now required at all direct-metered consumption points. The number of wiring diagrams has also been reduced.
These changes require extensive modifications to our product range, which cannot be implemented overnight. The applicable version of the connection requirements depends on the date of the connection agreement or agreement on a future connection agreement concluded with the distributor. If such an agreement was signed before these Connection Requirements were issued, the previous requirements in force when the agreement was concluded continue to apply.

The changes apply to all electricity meter enclosures.

  • Section 1.2 Terminology adds the terms Digital communication channel, Non-interval metering, Interval metering and Reconstruction of an electricity meter enclosure. The term Switching element now also includes a relay box. The abbreviations section has also been expanded with several new abbreviations.
  • Section 2.2, covering the main house service line (HDV), now allows lines that cannot be routed inside masonry to be installed in non-detachable rigid or flexible conduits, which no longer have to be metal.
  • Section 2.4, on installing surge protection in the unmetered section, now requires protection against unauthorised interference for any upstream disconnecting or protective device as well.
  • Section 2.6, Total Stop and Central Stop arrangements, has been simplified. The former Total Stop paragraph has essentially been renamed Central Stop and slightly revised; the previous Central Stop paragraph has been deleted. The new Total Stop paragraph simply states that the Total Stop function is provided by the fuses in the main house service box (HDS).
  • Section 3.1, Location of the electricity meter enclosure, has been revised. Installation heights for enclosures and their components are now specified in a table rather than in the text. The table additionally specifies the positions of circuit breakers, locks, PEN bridges and test terminal blocks. The text on enclosure placement in buildings for people with disabilities has been removed.

Table 1: Installation heights for the electricity meter enclosure and its components

  • The final paragraph of section 3.1, about accepting the existing location of an enclosure serving several consumption points, has been slightly reworded to add the condition “provided it can be operated safely.”
  • Section 3.2.1, Electricity meter enclosures and distribution cores, has also changed. For a 6 × 6 mm triangular spindle key lock, the spindle must now pass to a depth of at least 12 mm. Where the signal is insufficient for remote meter reading, the distributor requires cooperation with antenna installation and a safe route for the antenna cable to a location with adequate signal. Where existing enclosures with a mounting board are accepted under certain conditions, the existing wooden, pertinax or rubber meter board must be replaced with a new one, for example a premix board. A new requirement states: “All components of the electricity meter enclosure must be suitable for the expected current load and the upstream protective device.”
  • Section 3.3.1, Interface types, has been revised for the new generation of AMM (smart) meters. Subsection 3.3.1.1 HAN (RS485 with DLMS/COSEM) has been added to specify this interface.
  • Section 3.4, Equipment of electricity meter enclosures, has also been amended. The list of permitted devices no longer includes an optocoupler and its power supply for the S0 pulse output, a metrological LED or optical-interface sensor, or a control relay. It now more generally includes equipment for processing and remotely transmitting the meter-interface output, upstream protection for the surge protective device, an antenna for remote transmission of PDS and customer data, and current transformers for customer energy-balance metering.
  • Section 3.4 now also requires any sub-meter to be labelled so it cannot be mistaken for the billing meter, for example “Sub-meter”.
  • New requirements have been added to section 3.4 for identifying consumption points in the enclosure. For houses and cottages, the consumption point must be marked with its plot or descriptive number. In apartment buildings, rows of garages and energy centres, each apartment (door or door frame) or non-residential space must have a number, and the corresponding meter, main circuit breaker and installation switch position must carry the same number.
  • The table of minimum dimensions for installing meters and switching devices in section 3.4 has changed. Until the end of 2025, a single-phase meter requires a space only 300 mm high and 180 mm wide. From 1 January 2026, a space 400 mm high and 200 mm wide will be required, the same as for a three-phase meter. The additional 50 mm of width previously required when installing one device is no longer necessary.
  • Section 3.4.1, Circuit breakers, has been amended. Some wording has changed, but the requirements for the breakers themselves appear unchanged.
  • Section 3.4.2, Conductor design and marking, has been slightly amended. It now specifies that an existing aluminium outgoing conductor to the user’s installation may be retained only when connected from the installation switch or from the outgoing terminal block in the meter enclosure.
  • The former section 3.4.3, Control relay, has been renumbered as 3.6.4. Its content is almost identical.
  • Section Disconnecting device at the output of the electricity meter enclosure, now numbered 3.4.3, has been reworded. The requirement to install an “installation switch” has been extended to all direct-metered enclosures. Although the section requires installation switches for newly established or reconstructed consumption points from the requirements’ effective date (1 February 2025), the free appendix VP_A — Table of applicability of the LV Connection Requirements to common activities says the switch is required only in enclosures manufactured after 1 January 2026 (see below). The text explains that when a consumption point needs to be switched off, for example at a holiday property, the installation switch should be used instead of the main circuit breaker to maintain the meter’s remote communications. The wording on the switch’s location has also been revised to allow it “even in the unmetered part of the electricity meter enclosure”. However, given its function, the switch must be installed in the metered circuit; the earlier wording, which allowed it in the sealable part of the enclosure, was less ambiguous. A new requirement specifies that a lever-operated switch must be installed vertically, with the lever pointing upwards when switched on.
  • Section 3.5.2, Conductor cross-sections and colour identification, again permits 1 mm2 conductors for control circuits and the power supply to control devices.
  • Section 3.6.1, on current transformers, adds a requirement for a sealable cover over the secondary terminals, accessible for safe sealing. It also requires the clamping screws of window-type current transformers to be de-energised, for example by using an insulating washer. The table assigning current transformers to main-breaker current ratings has been simplified; all ratings except 160 A now have just one current-transformer ratio.
    Table 4: Current transformer assignment to main circuit breaker current ratings
  • Section 3.6.3, on conductor design, cross-sections and colour identification for current-transformer metering, now states that wiring located outside the sealed section must be visible, protected in non-detachable rigid or flexible conduits (or equivalent), and installed as a cable. A 4 mm2 Cu protective conductor (PE) is now required to connect and earth the current-transformer input terminals. Minimum cross-sections of 4 mm2 for current circuits and 2.5 mm2 for voltage circuits are required even for distances up to 5 m. Requirements for cross-sections and the rated power of current transformers over distances greater than 5 m are no longer specified.
  • Section 3.9, Protection of electricity meter enclosures and other parts of unmetered installations against unauthorised interference, has minor changes. The cover of a disconnecting or protective device for a surge protective device must now be sealable if installed in the unmetered section. The requirements still do not mention sealing the plinth or base of a pillar-type enclosure.
  • Section 4, Technical equipment requirements for generation facilities connected to the LV distribution system, contains many minor wording and terminology changes. New clauses 4.1.8 and 4.2.5 state that a generating facility operating in island mode does not have to meet the active-power limitation requirement.
  • New section 8, Cooperation with the PDS, requires cooperation with the distributor and timely contact with its staff for certain activities.
  • As most wiring diagrams have changed, section 11, List of separate appendices (the diagram list) has also changed and the number of diagrams has been reduced. The enclosure wiring for two-rate metering, for a supply with PV, or for EMO is now identical. New diagram No. 2 (two-rate meter wiring, or single-rate meter wiring with generation and active-power limitation) replaces former diagrams 2, 3, 4, 5, 6 and 7. There is no longer a separate diagram for a shared supply. Diagrams now show their revision and effective dates to make it easier to identify the applicable version.
  • Changes have also been made to appendix VP_A — Table of applicability of the LV Connection Requirements to common activities. The columns for the main house service line and meter branches have been combined. The table emphasises that the maximum cross-section of 16 mm2 must be observed even when the main circuit-breaker rating is reduced. The installation-switch column under section 3.4.3 is now split into consumption points with and without generation. For new consumption points without generation, the switch is required in the metering enclosure only for enclosures manufactured after 1 January 2026.

...and a number of other minor changes.

Wiring diagram for a two-rate meter or a single-rate meter with generation and active-power limitation

The new Connection Requirements are effective from 1 February 2025.

The ČEZ Distribuce Connection Requirements and appendices can be downloaded here: ČEZ Distribuce connection requirements

Please note: Consumption points established under connection agreements or agreements on future connection agreements concluded before these Connection Requirements were issued remain subject to the previous requirements in force when those agreements were concluded.


We will incorporate the new requirements into our production of electricity meter enclosures in the coming days, so we can once again guarantee that our enclosures meet the new connection requirements!